AKK Natural Gas Pipeline Project – Hydrocarbons Technology
The Ajaokuta-Kaduna-Kano (AKK) pipeline is a 614km-long natural gas pipeline being developed by the Nigerian National Petroleum Corporation (NNPC).
Ajaokuta–Kaduna–Kano Natural Gas Pipeline
Images








Description
The Ajaokuta–Kaduna–Kano Natural Gas Pipeline is a pipeline planned to transport natural gas from Ajaokuta, in Kogi State to Kano, in Kano State, through several states and urban centers, as part of the Trans Nigeria Gas Pipeline. Construction of the AKKP commenced in July 2020. Wikipedia
Status: Under Construction
Length: 382 mi (615 km)
Diameter: 40 in (1,016 mm)
General direction: South to North
Web results
Funding, insecurity stall $2.8b AKK project, gas export
4 Aug 2022 — Barely six months to expected completion of the $2.8 billion Ajaokuta-Kaduna-Kano (AKK) pipeline project, indications emerged yesterday that the …
https://www.nsenergybusiness.com › …
Ajaokuta–Kaduna–Kano (AKK) Gas Pipeline – NS Energy
The Ajaokuta–Kaduna–Kano (AKK) pipeline is a 614km-long pipeline being developed by Nigerian National Petroleum Corporation (NNPC) to transport natural gas …
Project Type: Natural Gas Pipeline
Estimated Project Cost: £2.2bn ($2.8bn)
Expected Start of Construction: 2020
Location: Nigeria
https://nairametrics.com › … › Energy
Nigeria’s AKK gas pipeline project a target for European markets – Oilserv Limited
4 May 2022 — AKK gas project, when completed would boost the agricultural and manufacturing sectors, carbon footprint as part of measures to cut down on …
https://nairametrics.com › … › Energy
$2.8 billion AKK gas pipeline project to be completed by 2023 – NNPC – Nairametrics
15 Apr 2022 — The Nigerian National Petroleum Company Ltd. (NNPC) has revealed that the $2.8 billion Ajaokuta, Kaduna and Kano (AKK) gas pipeline project …
https://www.reuters.com › africa › n…
Nigeria’s AKK gas pipeline to open in early 2023, NNPC says | Reuters
15 Apr 2022 — Construction of the Ajaokuta-Kaduna-Kano (AKK) pipeline began in June 2020, with authorities promising it would help generate 3.6 gigawatts of …
Ajaokuta-Kaduna-Kano Gas Pipeline Project to begin operations in Q1 2023
15 Apr 2022 — The construction of the 614km AKK Pipeline project was flagged-off simultaneously in Kogi and Kaduna States by President Muhammadu Buhari in …
https://www.thisdaylive.com › nnpc-…
NNPC Expecting First Gas From AKK Pipeline in Q1 2023, Says Kyari
https://www.icirnigeria.org › akk-pi…
AKK Pipeline Project: NNPC targets first gas delivery in Q1 2023 – ICIR Nigeria
14 Apr 2022 — Construction of the 614-kilometre AKK pipeline project was flagged off simultaneously in Kogi and Kaduna states by President Muhammadu Buhari in …